RSE’s Modular Upgrade of Eela WTW Driving Industry Innovation

By December 2, 2025March 27th, 2026No Comments
RSE Modular build

Built in 1978, the existing plant has long faced challenges associated with coming to the end of its serviceable life – issues now being addressed through RSE’s innovative and modular engineering approach.

Appointed as Principal Contractor and Principal Designer, RSE is leading the full delivery of civil, MEICA, process engineering and commissioning of the works to replace the existing plant with a new 5.7Ml/d ceramic membrane treatment facility. The new works will deploy PWNT’s C37 CeraMac® ceramic membrane system, which RSE has developed into a state-of-the-art modular solution that enhances water quality and operational resilience.

Port of Cromarty

To minimise disruption and accelerate delivery, RSE has applied its innovative Design for Modular Assembly (DfMA) strategy, constructing 42 modular Transportable Treatment Units (TTUs) at its facility in Muir of Ord, before transporting them to Shetland. Each modular unit has made the 24-hour sea journey via the Port of Cromarty Firth to the Sullum Voe Oil Terminal before final road delivery and offload to site. RSE worked with the client and logistics partner, Malin Group to safely deliver the 42 modules, with a total lead time of seven months from factory to site.

“This project represents one of the most remote and logistically complex modular water treatment deployments in the UK, delivered at an unprecedented pace. Our modular approach allows for parallel construction, reduces programme risk, and significantly cuts carbon.”

Duncan Gillies, Senior Project Manager, RSE

The Eela WTW upgrade remains on schedule, with the first modular units having successfully arrived on-site in August 2025, commissioning scheduled to begin in January 2026 and water in to supply due in November 2026.